TECHNICAL ROAD PROJECTS SUMMARIES – MANICALAND PROVINCE

Click on a name or the "plus" sign to expand each button.

PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Ngundu - Tanganda Road reconstruction as the road was heavily potholed and impassable.
• Implementation agent is Department of Roads
• Contractor is Bitumen World Pvt Ltd
• Project Duration – 6 weeks
• Project started on 15 February and completed on 31 March 2018
• Project covered Manicaland Province, Chipinge RDC

After

Funding:

ZINARA
Cost of project was USD4,223,852.25

Scope of works: Rehabilitation

• Project covered 30km
• 100% surfacing [8m on 8m]
• 100% Reclamation/reconstruction/ recycling
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Chimanimani – Tilbury road construction to complete the outstanding section and ensure trafficability.
• Implementation agent is Department of Roads
• Contractor is Bitumen World Pvt Ltd
• Project Duration – 2 months
• Project started on 31 March 2018 to 31 May 2018
• Project covered Manicaland Province, Chimanimani RDC

After

Funding:

100% funded by ZINARA
Cost of Project was USD660,893.50

Scope of works: Rehabilitation

• Project covered 30km
• 100% surfacing [7m on 8m]
• 100% construction
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

Rusape – Nyanga road resealing

• Implementation agent is Department of Roads
• Project Duration – 2 months
• Project started on 18 August to 14 October 2017
• Project covered Manicaland Province, Nyanga RDC

After

Funding:

100% funded by ZINARA
Cost of Project was USD500,000.00

Scope of works: Rehabilitation

• Project covered 10km
• 100% surfacing [7m on 8m]
• 100% Pothole patching and slurry sealing

TECHNICAL ROAD PROJECTS SUMMARIES – MATEBELELAND SOUTH PROVINCE

Click on a name or the "plus" sign to expand each button.

PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Falcon Road needed widening due to increase in traffic, poor nature of carriageway and to also upgdrade the road.
• Rehabilitation of Esigodini to Falcon Road.
• Implementation agent is Umzingwane RDC.
• Project Duration – 2 months.
• Project started on 7th May 2018 and completed on 23rd July 2018.
• Project in Umzingwane District.

After

Funding:

ZINARA
Cost of Project was USD568,947.96

Scope of works: Rehabilitation

• Project covered 5,4km.
• 100 % reconstruction only.
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Paving of Mthwakazi Bus Terminus and new construction of Mthwakazi access roads
• Project Duration – 12 months
• Project started in November 2016 and completed on November 2017
• Project only covered Filabusi centre, the purpose was to uplift the face of Mthwakazi Business centre and make the area dusty and mud free

After

Funding:

100% funded by ZINARA
Cost of project was USD376,071.05

Scope of works: Rehabilitation

• Project covered 0.8km on paving and 1km on earthworks and surfacing of Mthwakazi access roads
• 50 % paving and 50% asphalt overlay, parking bays
• 100 % earthworks and surfacing of access roads (9m wide)
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Road reconstruction Kalipati Road.
• Project Duration – 3 months however the project took longer than expected due to bad weather and late payments.
• Project started on February 2018 and ended on 25 June 2018.
• Project in Gwanda Town

After

Funding:

100% funded by ZINARA
Cost of project was $294,470.19

Scope of works: Reconstruction

• Project covered 960m
• 100% earthworks
• 100% tack and seal.
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Road reconstruction Enterprise Crescent.
• Project Duration – 3 months however the project took longer than expected due to bad weather and late payments.
• Project started on February 2018 and ended on 25 June 2018.
• Project in Gwanda Town

After

Funding:

100% funded by ZINARA
Cost of project was $223,457.39

Scope of works: Reconstruction

• Project covered 600m
• 100% earthworks
• 100% tack and seal.
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Letoka Road(1100m)
• Project started on October 2017 and is still in progress
• Project in Gwanda Town.

After

Funding:

100% funded by ZINARA
Cost of Project was $70,756.50

Scope of works: Reconstruction

• Earthworks complete
• Priming complete
• Tack and seal left
• 1100m road reconstruction
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Jahunda Ultra Road(1300m)
• Project started on October 2017 and is still in progress
• Project in Gwanda Town.

After

Funding:

100% funded by ZINARA
Cost of Project was $100,287.01

Scope of works: Reconstruction

• Earthworks complete
• Priming complete
• Tack and seal left
• 1300m road reconstruction
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Mtukuri to Medium Shops(1300m)
• Project started on 23 December 2017 and is still in progress
• Project in Gwanda Town

After

Funding:

100% funded by ZINARA
Cost of Project was $327,477.10

Scope of works: Reconstruction

• Earthworks complete
• Waiting for priming
• 1300m road reconstruction
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Workshop to Heroes to Medium Shops(2200)
• Project started on 23 December 2017 and is still in progress
• Project in Gwanda Town

After

Funding:

100% funded by ZINARA
Cost of Project was $439,034.60

Scope of works: Reconstruction

• Earthworks complete
• Waiting for priming
• 2200m road reconstruction
PROJECT PICTURES PROJECT SUMMARY

Before

Project Description:

• Nare Shops to Medium Shops(700m)
• Project started on 23 December 2017 and is still in progress
• Project in Gwanda Town.

After

Funding:

100% funded by ZINARA
Cost of Project was $232,762.10

Scope of works: Reconstruction

• Earthworks complete
• Waiting for priming
• 700m road reconstruction